Issue - items at meetings - Procurement of Solar Photovoltaic Arrays for BHCC HRA Property

skip navigation and tools

Issue - meetings

Procurement of Solar Photovoltaic Arrays for BHCC HRA Property

Meeting: 18/07/2013 - Council (Item 26)

26 Home Energy Efficiency Update: Procurement of Solar Photovoltaic Arrays for Housing Revenue Account Property pdf icon PDF 64 KB

Additional documents:

Minutes:


Meeting: 19/06/2013 - Housing Committee (pre 2015) (Item 11)

11 Home Energy Efficiency Update: Procurement of Solar Photovoltaic Arrays for Housing Revenue Account Property pdf icon PDF 111 KB

Report of Executive Director – Environment, Development & Housing (copy attached).

Decision:

RESOLVED:

 

That Housing Committee –

(1) Notes an update of the optoin appraisal for a large scale installation of Solar PV’s to housing stock.

(2) Approves the procurement of a contract for the supply and installation of Solar Photovoltaic Arraus to HRA owned dwellings for up to 12 months with two extensions of up to 12 months each if required, subject to satisfactory perfromance of the contractor.

(3) Grants delegated authority to the Executive Director Environment, Development & Housing, in consultation with Director of Finance & Resources, to award the contract for up to 12 months following the recommendations of the evaluation panel, and approve two extensions to the contract of up to 12 months each if required, subject to satisfactory performance of the contractor.

Minutes:

11.1         The Committee considered the report of the Executive Director Environment Development and Housing which provided an update on home energy efficiency, and the procurement of solar photovoltaic arrays for Housing Revenue Account properties.  Mr Reid, Head of Housing Strategy, presented the report.

 

11.2         The Chair thanked officers for the report, and noted that the cost of the installation seemed high. The Chair hoped that where possible local companies would be used.

 

11.3         Councillor Peltzer Dunn referred to the recommendations and asked whether the intention was to be a one year contract with an extension thereafter. Mr Reid confirmed that there would be a one year contract with a view to extending it for up to three years. Councillor Peltzer Dunn asked whether after the contract was awarded if any notice had to be given if the intention was to extend. The Chair said the officer who would be able to answer that was not at the meeting, and so a written response would be provided.

 

11.4         Councillor Mears referred to recommendation 2.3 and asked for confirmation that the Executive Director Environment Development and Housing had the authority to award the contract. The Chair confirmed he did.

 

11.5         Councillor Duncan referred to paragraph 4.2 of the report, and asked that leaseholders were consulted even though there was no requirement to.

 

11.6    RESOLVED:

 

That Housing Committee –

(1) Notes an update of the option appraisal for a large scale installation of Solar PV’s to housing stock.

 

(2) Approves the procurement of a contract for the supply and installation of Solar Photovoltaic Arrays to HRA owned dwellings for up to 12 months with two extensions of up to 12 months each if required, subject to satisfactory performance of the contractor.

 

(3) Grants delegated authority to the Executive Director Environment, Development & Housing, in consultation with Director of Finance & Resources, to award the contract for up to 12 months following the recommendations of the evaluation panel, and approve two extensions to the contract of up to 12 months each if required, subject to satisfactory performance of the contractor.


 


Brighton & Hove City Council | Hove Town Hall | Hove | BN3 3BQ | Tel: (01273) 290000 | Mail: info@brighton-hove.gov.uk | how to find us | comments & complaints