Decision - Royal Pavilion Estate Capital Project Phase 2
navigation and tools
Find it
You are here - Home : Council and Democracy : Councillors and Committees : Decision details
Decision details
Royal Pavilion Estate Capital Project Phase 2
Decision Maker: Policy, Resources & Growth Committee
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
Description of proposed Phase 2 works to the
Royal Pavilion and Garden. Report seeks authority to submit funding
applications to carry out works, particularly a HLF Round 1 and
Round 2 bid for funding to carry out works to the Royal Pavilion,
and council commitment to match funding,
Decision:
1) That Policy & Resources Committee notes the progress made to date on the Royal Pavilion Estate capital project and the works taking place at Brighton Dome to complete Phase 1 outlined in paragraph 3.4.
2) That Policy, Resources & Growth Committee agrees that a Round 1 Heritage Lottery Fund bid is submitted for Phase 2 works as described in paragraph 3.8 and that, should this bid be successful, a Round 2 bid then be prepared and submitted to the Heritage Lottery Fund.
3) That Policy, Resources & Growth Committee notes that Historic England has placed the Grade II listed Royal Pavilion Garden on the At Risk Register and the Royal Pavilion & Museums has commissioned a Conservation Plan and Management & Maintenance Plan to address the issues raised and put in place measures for future conservation and management of the Garden to achieve substantial improvements and the removal of the Garden from the At Risk register.
4) That Policy, Resources & Growth Committee earmarks £1.0million of unallocated capital resources to support the Royal Pavilion Estate Capital Project Phase 2.
Report author: Richard Davies
Publication date: 01/12/2017
Date of decision: 30/11/2017
Decided at meeting: 30/11/2017 - Policy, Resources & Growth Committee