Decision - Royal Pavilion Estate Capital Project Progress Up-date
navigation and tools
Find it
You are here - Home : Council and Democracy : Councillors and Committees : Decision details
Decision details
Royal Pavilion Estate Capital Project Progress Up-date
Decision Maker: Policy, Resources & Growth Committee
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
Up-date report on project actions and funding
model since last report in April 2016.
Decision:
RESOLVED:
1) That the Committee notes the progress made to date on the Royal Pavilion Estate capital project Phase 1 and approves:
a) The revised expenditure and funding model of £21.493m as detailed in the part 2 report (for the expenditure) and paragraph 3.14 (for the income).
b) Council borrowing of £2.704m to be financed by BDFL as set out in paragraph 3.14
c) Delegated authority to the Executive Director for Economy Environment & Culture and Executive Director Finance & Resources to increase the budget and implement the option of further borrowing capped at a level which is affordable for BDFL to finance (as set out in paragraphs 3.15, 3.16 and 7.2) should the tender cost estimates be higher than anticipated,
2) That Policy, Resources & Growth Committee notes the financial implications in section 7 and agrees that the Executive Director for Economy Environment & Culture and Executive Director Finance & Resources may implement the option of further borrowing to mitigate financial risks set out in paragraphs 7.3 and 7.5.
Report author: Richard Davies
Publication date: 26/10/2016
Date of decision: 13/10/2016
Decided at meeting: 13/10/2016 - Policy, Resources & Growth Committee